Feasibility Study for South Black Sea Region- İyisu, Kestanelik and Çankaya Dams and Hydroelectric Plants

  • Financing : -
  • Service : -
  • Employer : -
  • Project Duration : -

The purpose of this study is to determine optimum use of Arakli River between 0 and 560 m altitudes for energy production. Planning, preliminary engineering design and feasibility studies are carried out for these 3 dams and Hydroelectric Power Plant. Benefits such as water supply for irrigation are analyzed.

Provided Services:
Project Characteristics

Çankaya Dam and HPP
Rockfill dam with 105 m crest height
Installed capacity=29 MW
Annual energy production=134 million kWh

Kestanelik Dam and HPP
Rockfill dam with 30 m crest height
Installed capacity=13 MW
Annual energy production=66 million kWh

İyisu Dam and HPP
Rockfill dam with 30 m crest height
Installed capacity=13 MW
Annual energy production=66 million kWh

Studies and Engineering
Stability conductivity studies for the reservoirs
Positioning of optimum dam axis
Hydrometric and hydrological studies
Selection of most economical dam types, heights and dam sections
Selection of Hydroelectrical Power Plant installed capacity
Environmental Impact Assesment

Concept Design
Consept design of the dam, spillways, bottom discharge structures, water intake, pressurized pipes, power plant, switchyard,energy, energy transmission lines and other related structures

Feasibility Study
Feasibility study of the 3 dams and HPP including irrigation investments.